This project is located in The Eastern Azarbaijan Province, and includes the following processes:
A. Constructional works
1-Embankments, Drilling and grouting in side banks.
2-Agricultural outlet structures and Left and right control buildings
3-Spillway structures and Left and right power plants
4-Second stage of Diversion
-Excavation the ending of right and left outlet canals.
-Removing dykes and implementation of intermediate dyke.
-Construction and waterproofing of intermediate dyke.
5-Dam body -intermediate section.
6-Left and right spillway structures -final stage.
7-Catchment basins for Khod Afarin dam.
8-Supplementary works, asphalt and lighting system of crest.
B.First stage of hydro mechanical, electrical and control instruments.
1.Bottom tipper system.
2.Hydro mechanical instruments of power plant.
3.Diversion gate.
4.Designing, supply, production, transportation and installation of all Electricity and control elements.
5.Training of employer personnel.
6.Checking and completing the designs of frame lid of service, emergency, electricity and control gates.
Major operation activities are :
Excavation | 1,240,000 Cub.m |
Shell Gravel | 951,326 Cub.m |
Rockfill | 200,000 Cub.m |
Clay | 170,210 Cub.m |
Coarse filter | 87,000 Cub.m |
Fine filter | 93,800 Cub.m |
Rip-Rap | 33,000 Cub.m |
Bar work | 15,245 Ton |
Form work | 97,844 Sq.m |
Concrete work | 218,410 Cub.m |