Tohid Metro Station (E4),and the 1280 m,tunnel of Line 4,Tehran

Implementing operations in Tohid Metro Station (E4) , and the 1280 m. tunnel of Line 4:

1. Structure and guard structure of the station

2. Station's architecture

3. Station's electrical and mechanical installations

4. Tunnel ventilator (E4-D4)

5. 1280 m. Tunnel

Tohid Station has an area of 11550 square meters and includes the following items

Ticket Hall: 5950 square meters, platform level: 440 square meters, below platform level

1200 square meters, a unit of tunnels: 1280 meters

Major operation activities are :

Station Excavation 126,000Cub.m
Pile Excavation 2,534meters
Tunnel Excavation 85,000Cub.m
Bar Work 5,460Ton
Framing 33,748Sq.m
Formwork in the tunnel 30,343Sq.m
Concrete 59,879Cub.m
Shotcrete 68,000Sq.m
Heavy steel works 2,130Ton