Implementing operations in Tohid Metro Station (E4) , and the 1280 m. tunnel of Line 4:
1. Structure and guard structure of the station
2. Station's architecture
3. Station's electrical and mechanical installations
4. Tunnel ventilator (E4-D4)
5. 1280 m. Tunnel
Tohid Station has an area of 11550 square meters and includes the following items
Ticket Hall: 5950 square meters, platform level: 440 square meters, below platform level
1200 square meters, a unit of tunnels: 1280 meters
Major operation activities are :
Station Excavation | 126,000Cub.m |
Pile Excavation | 2,534meters |
Tunnel Excavation | 85,000Cub.m |
Bar Work | 5,460Ton |
Framing | 33,748Sq.m |
Formwork in the tunnel | 30,343Sq.m |
Concrete | 59,879Cub.m |
Shotcrete | 68,000Sq.m |
Heavy steel works | 2,130Ton |